Project Phases
Preliminary studies (winds, environmental elements) Since September 2005
Bid deposit to Hydro-Québec July 2010
Acceptance of the project from Hydro-Québec December 2010
Open house session September 2011
Environmental impact assessment deposit End of Fall 2011
Admissibility notification from the MDDEP Spring 2012
Information and public consultation period (BAPE) 45-day duration Summer 2012
BAPE public hearings, if necessary, and environmental analysis of the project Fall 2012
Minister's recommendation (MDDEP) and Cabinet’s decision (order in council) Winter 2013
Preparation of the construction work Winter 2013
Construction Work Summer 2013-2014
Comissioning December 2014
|