Project Phases
Phase 1 Conducted preliminary studies Wind studies and configuration settings September 2005
Phase 2 Submission of the bid to Hydro-Quebec September 2007
Phase 3 First public consultation: Project Presentation December 2007
Phase 4 Unveiling the results of tenders by Hydro-Quebec May 2008
Phase 5 Avis de projet for the MDDEP Receipt of the Directive for the achievement of impact July 2008
Phase 6 Second public consultation: Project Presentation January 2009
Phase 7 Filing of Environmental Impact Assessment MDDEP Realization of the EIA Study February 2009
Phase 8 Analysis of the admissibility of the impact study Receiving notice of admissibility MDDEP June 2009
Phase 9 Period of information and public consultation BAPE public hearing (if requested) November 2009
Phase 10 Environmental Analysis Project BAPE report Report analysts MDDEP February 2010
Phase 11 Recommendation of the Minister (MDDEP) Decision of the Council of Ministers (Decree) Summer 2010
Phase 12 Start of construction Permits, licenses, control and monitoring Fall 2010
Phase 13 Construction Phase I and II: Pathways, foundations, collector system Summer-Fall 2011, 2012, 2013
Phase 14 Commissioning Project Commencement of deliveries of energy to Hydro-Quebec Phase 1 (150 MW): December 1, 2012 Phase 2 (150 MW): December 1, 2013 December 2012/2013
|