Project Phases
Phase 1 Preliminary studies Wind resource assessment and wind farm layout July 2006
Phase 2 Submission of “Avis de projet” (project notice) to MDDEP (Quebec ministry of sustainable development, environment and parks) Guidelines received for conducting environmental impact assessment (EIA) August 2007
Phase 3 Bid submitted to Hydro-Québec September 2007
Phase 4 First public consultation: Presentation of project December 2007
Phase 5 Results of Hydro-Québec Call for Tenders announced May 2008
Phase 6 Second public consultation: Presentation of project December 2008
Phase 7 Third public consultation: Presentation of project October 2009
Phase 8 Environmental Impact Assessment conducted and submitted to MDDEP December 2009
Phase 9 Analysis of the admissibility of the EIA Notice of admissibility received from MDDEP June 2010
Phase 10 Information and public consultation period BAPE public hearings November 2010
Phase 11 Environmental analysis of project BAPE report Analysis report submitted to MDDEP March 2011
Phase 12 Recommendations made by MDDEP Decision of Council of Ministers (Decree) Summer-Fall 2011
Phase 13 Start of construction Permits and approvals received; environmental monitoring Summer-Fall 2011
Phase 14 Project commissioning Commencement of deliveries of energy to Hydro-Québec December 2012
|