Project Phases
Phase 1 Conducted preliminary studies Wind studies and configuration settings July 2006
Phase 2 Filing of the Notice of Proposed MDDEP Receipt of the Directive for the achievement of impact August 2007
Phase 3 Submission of the bid to Hydro-Quebec September 2007
Phase 4 First public information: Project presentation December 2007
Phase 5 Unveiling the results of tenders by Hydro-Quebec May 2008
Phase 6 Second public information: Project presentation December 2008
Phase 7 Third public information: Project presentation October 2009
Phase 8 Filing of Environmental Impact Assessment MDDEP Realization of the impact on the environment December 2009
Phase 9 Analysis of the admissibility of the impact study Receiving notice of admissibility MDDEP June 2010
Phase 10 Period of information and public consultation BAPE public hearing (if requested) November 2010
Phase 11 Environmental Analysis Project BAPE report Report analysts MDDEP March 2011
Phase 12 Recommendation of the Minister (MDDEP) Decision of Council of Ministers (Decree) Summer-Fall 2011
Phase 13 Start of construction Permits, licenses, monitoring, control and monitoring Summer-Fall 2011
Phase 14 Commissioning Project Commencement of deliveries of energy to Hydro-Quebec December 2012
|