Project Phases

Phase 1
Early investigations on the site
Wind studies and configuration settings
2006

Phase 2
Submission of the bid to Hydro-Quebec
September 2007

Phase 3
Unveiling the projects selected by Hydro-Quebec
May 2008

Phase 4
Filing of the Notice of Proposed MDDEP
Receipt of the Directive for the achievement of impact
June 2009

Phase 5
First Public information: Project presentation 
June 2010

Phase 6
Filing of Environmental Impact Assessment MDDEP
Realization of the impact on the environment
Winter 2011

Phase 7
Analysis of the admissibility of the impact study
Receiving notice of admissibility MDDEP
Fall 2011

Phase 8
Period of information and public consultation
BAPE public hearing (if requested)
Winter 2012

Phase 9
Environmental Analysis Project
BAPE report
Environmental analyse by MDDEP
Summer 2012

Phase 10
Recommendation of the Minister (MDDEP)
Decision of Council of Ministers (Decree) 
Fall 2012

Phase 11
Obtaining permits and approvals in preparation for the
construction
Winter 2013

Phase 12
Construction
2013, 2014, 2015

Phase 13
Commissioning Project
Commencement of deliveries of energy to Hydro-Quebec
Phase 1: 150 MW
Phase 2: 200 MW
December 2014/2015