Project Phases
Phase 1 Early investigations on the site Wind studies and configuration settings 2006
Phase 2 Submission of the bid to Hydro-Quebec September 2007
Phase 3 Unveiling the projects selected by Hydro-Quebec May 2008
Phase 4 Filing of the Notice of Proposed MDDEP Receipt of the Directive for the achievement of impact June 2009
Phase 5 First Public information: Project presentation June 2010
Phase 6 Filing of Environmental Impact Assessment MDDEP Realization of the impact on the environment Winter 2011
Phase 7 Analysis of the admissibility of the impact study Receiving notice of admissibility MDDEP Fall 2011
Phase 8 Period of information and public consultation BAPE public hearing (if requested) Winter 2012
Phase 9 Environmental Analysis Project BAPE report Environmental analyse by MDDEP Summer 2012
Phase 10 Recommendation of the Minister (MDDEP) Decision of Council of Ministers (Decree) Fall 2012
Phase 11 Obtaining permits and approvals in preparation for the construction Winter 2013
Phase 12 Construction 2013, 2014, 2015
Phase 13 Commissioning Project Commencement of deliveries of energy to Hydro-Quebec Phase 1: 150 MW Phase 2: 200 MW December 2014/2015
|