Project Phases
Phase 1 Preliminary studies of the site Wind resource assessment and wind farm layout 2006
Phase 2 Bid submitted to Hydro-Quebec September 2007
Phase 3 Results of Hydro-Québec Call for Tenders announced May 2008
Phase 4 Submission of “Avis de projet” (project notice) to MDDEP (Quebec ministry of sustainable development, environment and parks) Guidelines received for conducting environmental impact assessment (EIA) June 2009
Phase 5 First Public Consultation: Presentation of project June 2010
Phase 6 Environmental Impact Assessment conducted and submitted to MDDEP March 2011
Phase 7 Analysis of the admissibility of the EIA Notice of admissibility received from MDDEP Fall 2011
Phase 8 Information and public consultation period BAPE public hearings Winter 2012
Phase 9 Environmental analysis of project BAPE report Analysis report submitted to MDDEP Summer 2012
Phase 10 Recommendations made by the MDDEP Decision of Council of Ministers (Decree) Fall 2012
Phase 11 Permits and approvals received in preparation for construction Winter 2013
Phase 12 Construction 2013, 2014, 2015
Phase 13 Project commissioning Commencement of deliveries of energy to Hydro-Québec Phase 1: 150 MW Phase 2: 200 MW December 2014/2015
|