Saint Robert Bellarmin - 80 MW

  

The Saint- Robert Bellarmin wind project is located south of the municipality of the same name in the Granit RCM, halfway between the towns of Lac-Mégantic and Saint-Georges de Beauce.

Scheduled to start operating on summer 2012, the project will consist of 40 turbines of 2 MW each and will require an investment of nearly $ 200 million, 60% of which will be with Quebec businesses.

  Liaison Committee  

The Liaison Committee contributes to the development of the wind farm of Saint-Robert Bellarmin, in respect of the host. Composed of municipal representatives and groups interested in the project, the Liaison Committee ensures that all interested parties in the community are represented in the development of the wind farm.

Read More >>

     
  Liaison Office  

The Liaison Office was established so EDF EN Canada can meet with the community and project stakeholders throughout the development process. We want to know the opinion of the population and our Liaison Officer, Felix Destrijker, provides a strong link between the actions of the company and the various organizations...

Read More >>

     
  Project Phases  

Phase 1
Conducted preliminary studies
Wind studies and configuration settings
September 2005

Read More >>

     
  Key Project Figures  

Installed power
80 MW

Read More >>

     
  PDF Downloads  

Project Newsletters

Environmental Impact Studies

EDF EN Canada is committed to continuing communication with the public regarding the project's progression. To this end, several steps have been taken to ensure good communication including; the establishment of the Liaison office in Saint-Robert Bellarmin, and the publication of the quarterly newsletter, The Éole-Lien.

Read More >>

In Quebec, each wind project of 10 MW and above (Regulation on Assessment and review of impacts on the environment, art. 2.1) is subject to the environmental impacts evaluation process and review under Articles 31.1 and must follow the Act Environmental Quality Act (RSQ, c. Q-2) and be authorized by a government decree.

Read More >>

     
  Press  
06/27/11: EDF EN Canada obtains authorization to begin construction on Saint Robert Bellarmin