Project Phases
Phase 1 Conducted preliminary studies Wind studies and configuration settings September 2005
Phase 2 Submission of the bid to Hydro-Quebec September 2007
Phase 3 Unveiling the results of tenders by Hydro-Quebec May 2008
Phase 4 Relocation to Saint - Robert Bellarmin- Fall / Winter 2009-2010
Phase 5 First public consultation: Project Presentation Fall 2009
Phase 6 Filing of Environmental Impact Assessment MDDEP Realization of the EIA Study February 2010
Phase 7 Analysis of the admissibility of the impact study Receiving notice of admissibility MDDEP June 2010
Phase 8 Period of information and public consultation BAPE public hearing October 2010
Phase 9 Environmental Analysis Project BAPE report November 2010
Phase 10 Recommendation of the Minister (MDDEP) Decision of Council of Ministers (Decree) June 2011
Phase 11 Start of construction Permits, licenses, monitoring, control and monitoring Summer 2011
Phase 12 Commissioning Project Commencement of deliveries of energy to Hydro-Quebec Summer 2012
|