Project Phases

Phase 1
Conducted preliminary studies
Wind studies and configuration settings
September 2005

Phase 2
Submission of the bid to Hydro-Quebec
September 2007

Phase 3
Unveiling the results of tenders by Hydro-Quebec
May 2008

Phase 4
Relocation to Saint - Robert Bellarmin-
Fall / Winter 2009-2010

Phase 5
First public consultation: Project Presentation
Fall 2009

Phase 6
Filing of Environmental Impact Assessment MDDEP
Realization of the EIA Study
February 2010

Phase 7
Analysis of the admissibility of the impact study
Receiving notice of admissibility MDDEP
June 2010

Phase 8
Period of information and public consultation
BAPE public hearing
October 2010

Phase 9
Environmental Analysis Project
BAPE report
November 2010

Phase 10
Recommendation of the Minister (MDDEP)
Decision of Council of Ministers (Decree)
June 2011

Phase 11
Start of construction
Permits, licenses, monitoring, control and monitoring
Summer 2011

Phase 12
Commissioning Project
Commencement of deliveries of energy to Hydro-Quebec
Summer 2012