Project Phases
Phase 1 Preliminary studies Wind resource assessment and wind farm layout September 2005
Phase 2 Bid submitted to Hydro-Québec September 2007
Phase 3 Results of Hydro-Québec Call for Tenders announced May 2008
Phase 4 Relocation to Saint-Robert-Bellarmin Fall/Winter 2009-2010
Phase 5 First public consultation: Presentation of project Fall 2009
Phase 6 Environmental Impact Assessment (EIA) conducted and submitted to MDDEP February 2010
Phase 7 Analysis of the admissibility of the EIA Notice of admissibility received from MDDEP June 2010
Phase 8 Information and public consultation period BAPE public hearings October 2010
Phase 9 Environmental analysis of project BAPE report November 2010
Phase 10 Recommendations made by MDDEP Decision of Council of Ministers (Decree) June 2011
Phase 11 Start of construction Permits and approvals received; environmental monitoring Summer 2011
Phase 12 Project commissioning Commencement of deliveries of energy to Hydro-Québec Summer 2012
|